Indicative CAPEX in Philippines
Envelope, plant & installation
USD 1,570,055
Monitoring & alarms
USD 10,800
Automation / racking
Not included
Total indicative CAPEX
USD 1,753,561
Planning range: USD 1,402,849 – USD 2,279,630, reflecting building condition, ground works, electrical infrastructure and Philippines installation rates.
This sits inside the USD 250,000+ commercial project range ColdMatch supports.
Indicative annual OPEX in Philippines
Average refrigeration load
155 kW
Grid electricity
1,354,063 kWh
Electricity cost
USD 216,650
Standby generation (850 h/yr)
USD 35,961
Maintenance & spares
USD 61,725
Monitoring & compliance
USD 4,620
Total annual OPEX
USD 380,556
Planning range: USD 323,473 – USD 456,667. Energy (electricity plus fuel) accounts for about 66% of the annual cost at these inputs — USD 152 per m³ per year.
Turn this Philippines budget into a supplier-ready RFQ so quotations cover the same scope, redundancy and documentation.