Schedule

Cold Storage Project Timeline Guide

Refrigeration projects take longer than most buyers expect — mostly because of decisions that could have been made earlier. This timeline guide tells you what's realistic per project scale.

Expert summary

Modular cold room: 12–20 weeks. Mid-size cold storage warehouse: 8–14 months. Industrial ammonia plant: 14–24 months. Add 4–8 weeks for permits and financing.

Modular / walk-in cold room

RFQ 2 weeks, award 2 weeks, manufacture 4–8 weeks, shipping 2–4 weeks, install & commission 2–4 weeks. Total 12–20 weeks.

Mid-size cold storage warehouse (3,000–10,000 m³)

Planning 6–10 weeks, RFQ 6–8 weeks, contract 4–6 weeks, engineering 8–12 weeks, construction 20–28 weeks, commissioning 4–6 weeks. Total 8–14 months.

Industrial ammonia plant

Planning 10–14 weeks, permits 8–16 weeks, RFQ 8–12 weeks, contract 6–10 weeks, engineering 16–24 weeks, construction 30–48 weeks, HAZOP + commissioning 8–12 weeks. Total 14–24 months.

Where projects slip

Permits (add 4–12 weeks in some markets), grid connection (up to 6 months), imported equipment customs, weather (rainy season), and slow FAT resolutions.

FAQ

Frequently asked questions

Can I compress the schedule?

Yes — invest in planning and pre-order long-lead items (compressors, panels, doors) at award instead of after final drawings.

What's the longest single item?

Screw compressors for large ammonia plants — 20–28 weeks factory lead time. Order early.