Offline — reconnect before saving or submitting. Changes on this page have not been sent.

Schedule

Cold Storage Project Timeline Guide

Refrigeration projects take longer than most buyers expect — mostly because of decisions that could have been made earlier. This timeline guide tells you what's realistic per project scale.

Expert summary

Modular cold room: 12–20 weeks. Mid-size cold storage warehouse: 8–14 months. Industrial ammonia plant: 14–24 months. Add 4–8 weeks for permits and financing.

Modular / walk-in cold room

RFQ 2 weeks, award 2 weeks, manufacture 4–8 weeks, shipping 2–4 weeks, install & commission 2–4 weeks. Total 12–20 weeks.

Mid-size cold storage warehouse (3,000–10,000 m³)

Planning 6–10 weeks, RFQ 6–8 weeks, contract 4–6 weeks, engineering 8–12 weeks, construction 20–28 weeks, commissioning 4–6 weeks. Total 8–14 months.

Industrial ammonia plant

Planning 10–14 weeks, permits 8–16 weeks, RFQ 8–12 weeks, contract 6–10 weeks, engineering 16–24 weeks, construction 30–48 weeks, HAZOP + commissioning 8–12 weeks. Total 14–24 months.

Where projects slip

Permits (add 4–12 weeks in some markets), grid connection (up to 6 months), imported equipment customs, weather (rainy season), and slow FAT resolutions.

FAQ

Frequently asked questions

How ColdMatch Group works — independent B2B procurement and sourcing platform — ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, where the ColdMatch team reviews each buyer brief, contacts suitable third-party suppliers on the buyer's behalf and organizes their responses.