Cold Storage Project Timeline Guide
Refrigeration projects take longer than most buyers expect — mostly because of decisions that could have been made earlier. This timeline guide tells you what's realistic per project scale.
Modular cold room: 12–20 weeks. Mid-size cold storage warehouse: 8–14 months. Industrial ammonia plant: 14–24 months. Add 4–8 weeks for permits and financing.
Modular / walk-in cold room
RFQ 2 weeks, award 2 weeks, manufacture 4–8 weeks, shipping 2–4 weeks, install & commission 2–4 weeks. Total 12–20 weeks.
Mid-size cold storage warehouse (3,000–10,000 m³)
Planning 6–10 weeks, RFQ 6–8 weeks, contract 4–6 weeks, engineering 8–12 weeks, construction 20–28 weeks, commissioning 4–6 weeks. Total 8–14 months.
Industrial ammonia plant
Planning 10–14 weeks, permits 8–16 weeks, RFQ 8–12 weeks, contract 6–10 weeks, engineering 16–24 weeks, construction 30–48 weeks, HAZOP + commissioning 8–12 weeks. Total 14–24 months.
Where projects slip
Permits (add 4–12 weeks in some markets), grid connection (up to 6 months), imported equipment customs, weather (rainy season), and slow FAT resolutions.
Frequently asked questions
How ColdMatch Group works — independent B2B procurement and sourcing platform — ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.
Next steps for your project
Wherever your project stands — early feasibility, budget approval or supplier selection — these are the practical next steps. Every stage is supported by our human expert team, and requesting quotes is free and supplier-neutral for buyers and project owners.