12,000 m³ seafood cold storage & blast freezer — Vietnam

An export-grade seafood processor needed a multi-temperature facility combining IQF tunnels, blast freezers and long-term storage to meet EU/Japan buyer requirements.

Da Nang, Vietnam 12,000 m³ −25 °C storage, −40 °C blast 19 months, concept to full production

Challenge

  • Existing facility could not blast-freeze shrimp fast enough for export specs.
  • Energy costs rising 14% year-on-year on R22 plant nearing end-of-life.
  • HACCP and BRCGS audit gaps on temperature traceability.

ColdMatch solution

  • ColdMatch sourced 3 shortlisted EPCs from Korea, Italy and Vietnam.
  • Selected NH₃/CO₂ cascade plant with IoT monitoring (logger + cloud).
  • Phased construction allowed processing to continue during build.
ColdMatch handled the EPC tender across three countries — the savings paid for the upgrade in under four years.
Operations Director, seafood exporter
End-to-end delivery

How this project was delivered — planning to commissioning

Multi-country EPC tender, phased construction on a live site. Total programme: 19 months, concept to full production.

  1. 1

    Planning & feasibility

    Months 1–4
    • Throughput study across shrimp, pangasius and value-added lines, including seasonal peaks.
    • Heat-load and freezing-curve modelling to size blast capacity against export specifications.
    • Capex and operating-cost case built for three plant architectures before any supplier contact.

    Milestone: Approved technical brief and budget envelope signed off by the board.

  2. 2

    Permitting & approvals

    Months 4–7
    • Provincial construction and industrial-zone approvals for the extension footprint.
    • Ammonia handling permit, safety distance study and emergency response plan.
    • Environmental discharge and refrigerant registration filed with the authorities.

    Milestone: Construction permit and ammonia safety approval issued.

  3. 3

    Procurement & build-out

    Months 7–15
    • Three shortlisted EPCs from Korea, Italy and Vietnam tendered on one common specification.
    • Panel envelope, NH₃/CO₂ cascade plant room and IQF tunnels installed in two phases.
    • Processing kept running throughout by sequencing the works around production windows.

    Milestone: Mechanical completion of both phases with the plant charged and leak-tested.

  4. 4

    Testing & validation

    Months 15–18
    • Pull-down and freezing-curve testing against contractual blast-cycle times.
    • Temperature mapping of every chamber, loaded and unloaded, across 72-hour cycles.
    • HACCP and BRCGS traceability evidence assembled from the IoT logger platform.

    Milestone: Performance guarantees verified and audit pack accepted.

  5. 5

    Commissioning & handover

    Months 18–19
    • Operator training on plant control, alarm response and defrost strategy.
    • Spares package, service contract and remote monitoring handover.
    • 12-month energy benchmark baseline agreed with the operator.

    Milestone: Facility handed over in full production with warranty and service plan active.