Multi-temp food distribution centre — Saudi Arabia

Major QSR & retail supplier consolidating five legacy warehouses into a single ASRS-equipped multi-temperature distribution centre.

Riyadh, Saudi Arabia 32,000 m² multi-temp DC Ambient, +2 °C, −18 °C, −25 °C 20 months, site selection to network go-live

Challenge

  • Vision 2030 service-level targets across 1,800 SKUs.
  • 45 °C ambient + Ramadan demand peaks.
  • Energy cap from local utility post-2024 tariff reform.

ColdMatch solution

  • CO₂ transcritical refrigeration with heat-recovery for offices.
  • ASRS with frozen pick module and multi-temp pick-to-light.
  • ColdMatch ran shortlist of 4 EPCs + 3 ASRS integrators.
End-to-end delivery

How this project was delivered — planning to commissioning

Turnkey multi-temperature DC with retail-network integration. Total programme: 20 months, site selection to network go-live.

  1. 1

    Planning & feasibility

    Months 1–4
    • Network study: order profiles, store replenishment frequency and dock cycles.
    • Zone sizing across ambient, chilled and frozen against forecast SKU growth.
    • Land, power and cooling strategy assessed for high-ambient operation.

    Milestone: Facility concept and capacity plan approved with expansion headroom.

  2. 2

    Permitting & approvals

    Months 4–8
    • Municipality building permit and industrial land-use approvals.
    • Civil defence fire strategy for high-bay frozen storage.
    • Food authority storage registration prepared in parallel with design.

    Milestone: Building permit issued and food-authority pathway agreed.

  3. 3

    Procurement & build-out

    Months 8–16
    • Multi-temperature envelope, racking, dock levellers and airlocks installed.
    • Refrigeration plant and controls integrated with the warehouse management system.
    • Energy metering installed per zone for post-handover benchmarking.

    Milestone: Practical completion with all temperature zones constructed.

  4. 4

    Testing & validation

    Months 16–19
    • Pull-down, door-cycle and dock-seal testing under peak summer ambient.
    • Loaded temperature mapping per zone and cross-dock transition testing.
    • WMS-to-refrigeration data integration verified end to end.

    Milestone: Zones released for stock after mapping and integration sign-off.

  5. 5

    Commissioning & handover

    Months 19–20
    • Live pilot with a limited store cluster before full network cutover.
    • Shift handbooks, alarm escalation and service contract activated.
    • Energy and service-level baseline agreed for the first operating year.

    Milestone: Distribution centre live across the retail network.