← Case studies

Integrated meat processing & cold storage — Brazil

Beef exporter expanding capacity for halal and EU markets needed an integrated chilling, blast freezing and frozen storage line.

Goiás, Brazil 18,000 m³ + 2 blast tunnels 0 °C chill, −25 °C storage, −38 °C blast 24 months, concept to export throughput

Challenge

  • Throughput target: 280 t/day chilled, 120 t/day blast.
  • Power constraints required peak-shaving via thermal storage.
  • Halal segregation and EU traceability in one facility.

ColdMatch solution

  • NH₃ central plant with ice-bank thermal storage.
  • Conveyorised blast tunnels with automated retraction.
  • ColdMatch-managed tender across 5 international EPCs.
End-to-end delivery

How this project was delivered — planning to commissioning

Integrated process + refrigeration EPC with staged energisation. Total programme: 24 months, concept to export throughput.

  1. 1

    Planning & feasibility

    Months 1–5
    • Throughput modelling for 280 t/day chilled and 120 t/day blast capacity.
    • Grid capacity study and thermal-storage peak-shaving strategy.
    • Halal and EU segregation designed into the product flow and hygiene zoning.

    Milestone: Process flow and refrigeration concept frozen for tender.

  2. 2

    Permitting & approvals

    Months 5–10
    • Federal inspection service and EU establishment approval requirements mapped.
    • State environmental licence covering effluent, refrigerant and noise.
    • Utility connection agreement negotiated with the local distributor.

    Milestone: Environmental licence and export establishment pathway confirmed.

  3. 3

    Procurement & build-out

    Months 10–20
    • Chill halls, two blast tunnels and frozen storage built in a single civil programme.
    • Central ammonia plant with thermal storage installed and staged for partial energisation.
    • Hygiene-critical finishes, drainage and dock equipment installed under supervision.

    Milestone: First chill hall energised while the freezer package continues.

  4. 4

    Testing & validation

    Months 20–23
    • Chilling and blast curves verified against contractual throughput per shift.
    • Peak-demand testing to confirm thermal storage holds the site inside its grid limit.
    • Traceability and segregation audit rehearsals for EU and halal certification.

    Milestone: Throughput and demand guarantees demonstrated over sustained runs.

  5. 5

    Commissioning & handover

    Months 23–24
    • Shift-team training on plant operation, defrost and emergency shutdown.
    • Maintenance regime, spares and refrigerant management plan handed over.
    • Ramp-up plan to full export volume agreed with the operator.

    Milestone: Plant released to production and certification audits scheduled.

Planning the same project?

This project sits under the Develop a Food Processing Cold Chain objective. Start from the objective hub to scope capacity, permitting and budget before engaging suppliers.

More case studies
Get Free QuotesFind the Best Solution