Cold-chain project timeline generator
Enter a few project parameters — get an indicative phased schedule from feasibility to commissioning. For planning conversations with stakeholders, lenders and suppliers. Not a contractual schedule.
Cold storage / refrigerated warehouse
- Phase 1Feasibility & site surveyConcept, catchment / demand, site walk, utility check.4 wk16 Sept 2026 → 14 Oct 2026
- Phase 2Basic + detailed designFEED, layouts, load calculations, specifications.6 wk14 Oct 2026 → 25 Nov 2026
- Phase 3Supplier selection & PORFQ, technical & commercial evaluation, contract.5 wk25 Nov 2026 → 30 Dec 2026
- Phase 4Financing preparationBusiness plan, lender package, term sheet.4 wk30 Dec 2026 → 27 Jan 2027
- Phase 5Manufacturing / fabricationEquipment build, panels, controls, FAT.13 wk27 Jan 2027 → 28 Apr 2027
- Phase 6Shipping & logisticsSea/air freight, customs, inland transport.5 wk28 Apr 2027 → 02 Jun 2027
- Phase 7Site preparation & civil worksFoundations, floor, drainage, incoming utilities.8 wk02 Jun 2027 → 28 Jul 2027
- Phase 8Mechanical & electrical installationEnvelope, refrigeration, piping, electrical, controls.9 wk28 Jul 2027 → 29 Sept 2027
- Phase 9Testing & SATSite acceptance, pressure/leak, controls integration.3 wk29 Sept 2027 → 20 Oct 2027
- Phase 10Commissioning & handoverCool-down, training, documentation, warranty start.3 wk20 Oct 2027 → 10 Nov 2027
A realistic cold storage schedule has five phases: concept and specification (3–6 weeks), supplier selection and contracting (4–8 weeks), equipment manufacture and lead time (12–24 weeks), construction and installation (12–30 weeks, partly parallel), and commissioning plus temperature validation (4–8 weeks). Compressors and insulated panels are almost always the critical path.
Frequently asked questions
What has the longest lead time in a cold storage project?
Industrial compressors and screw packs at 12–24 weeks, followed by insulated panels and doors. Order these first.
How long is commissioning?
Four to eight weeks including pull-down, temperature mapping, alarm testing and documentation for certification.
Can construction and manufacturing overlap?
Yes — civil works and the envelope usually run in parallel with equipment manufacture, saving 2–4 months versus a sequential schedule.