Cold-chain project timeline generator

Enter a few project parameters — get an indicative phased schedule from feasibility to commissioning. For planning conversations with stakeholders, lenders and suppliers. Not a contractual schedule.

Indicative planning schedule only. Actual timelines depend on country, permitting, financing close, supplier lead times, logistics, site conditions and scope. Confirm milestones with your engineering & procurement team and suppliers.
Indicative schedule

Cold storage / refrigerated warehouse

Total duration
60 weeks
Handover ≈ 25 Dec 2027
  1. Phase 1
    Feasibility & site survey
    Concept, catchment / demand, site walk, utility check.
    4 wk
    31 Oct 2026 → 28 Nov 2026
  2. Phase 2
    Basic + detailed design
    FEED, layouts, load calculations, specifications.
    6 wk
    28 Nov 2026 → 09 Jan 2027
  3. Phase 3
    Supplier selection & PO
    RFQ, technical & commercial evaluation, contract.
    5 wk
    09 Jan 2027 → 13 Feb 2027
  4. Phase 4
    Financing preparation
    Business plan, lender package, term sheet.
    4 wk
    13 Feb 2027 → 13 Mar 2027
  5. Phase 5
    Manufacturing / fabrication
    Equipment build, panels, controls, FAT.
    13 wk
    13 Mar 2027 → 12 Jun 2027
  6. Phase 6
    Shipping & logistics
    Sea/air freight, customs, inland transport.
    5 wk
    12 Jun 2027 → 17 Jul 2027
  7. Phase 7
    Site preparation & civil works
    Foundations, floor, drainage, incoming utilities.
    8 wk
    17 Jul 2027 → 11 Sept 2027
  8. Phase 8
    Mechanical & electrical installation
    Envelope, refrigeration, piping, electrical, controls.
    9 wk
    11 Sept 2027 → 13 Nov 2027
  9. Phase 9
    Testing & SAT
    Site acceptance, pressure/leak, controls integration.
    3 wk
    13 Nov 2027 → 04 Dec 2027
  10. Phase 10
    Commissioning & handover
    Cool-down, training, documentation, warranty start.
    3 wk
    04 Dec 2027 → 25 Dec 2027
Direct answer

A realistic cold storage schedule has five phases: concept and specification (3–6 weeks), supplier selection and contracting (4–8 weeks), equipment manufacture and lead time (12–24 weeks), construction and installation (12–30 weeks, partly parallel), and commissioning plus temperature validation (4–8 weeks). Compressors and insulated panels are almost always the critical path.

Frequently asked questions

What has the longest lead time in a cold storage project?

Industrial compressors and screw packs at 12–24 weeks, followed by insulated panels and doors. Order these first.

How long is commissioning?

Four to eight weeks including pull-down, temperature mapping, alarm testing and documentation for certification.

Can construction and manufacturing overlap?

Yes — civil works and the envelope usually run in parallel with equipment manufacture, saving 2–4 months versus a sequential schedule.

Next steps for your project

Send these inputs to an RFQ

Your size, cost and load inputs are copied into the quote form, so you don't type them twice. Nothing is sent until you review and submit.

Free for buyers, no obligation. These figures are estimates, not quotes — our team reviews your request and contacts suitable suppliers on your behalf.

Project request

Submit your project for expert review

Send your requirements. A ColdMatch specialist reviews every request, prepares a brief and introduces suitable suppliers — free for buyers.