Planning Tool

Cold-chain project timeline generator

Enter a few project parameters — get an indicative phased schedule from feasibility to commissioning. For planning conversations with stakeholders, lenders and suppliers. Not a contractual schedule.

Indicative planning schedule only. Actual timelines depend on country, permitting, financing close, supplier lead times, logistics, site conditions and scope. Confirm milestones with your engineering & procurement team and suppliers.
Indicative schedule

Cold storage / refrigerated warehouse

Total duration
60 weeks
Handover ≈ 10 Nov 2027
  1. Phase 1
    Feasibility & site survey
    Concept, catchment / demand, site walk, utility check.
    4 wk
    16 Sept 202614 Oct 2026
  2. Phase 2
    Basic + detailed design
    FEED, layouts, load calculations, specifications.
    6 wk
    14 Oct 202625 Nov 2026
  3. Phase 3
    Supplier selection & PO
    RFQ, technical & commercial evaluation, contract.
    5 wk
    25 Nov 202630 Dec 2026
  4. Phase 4
    Financing preparation
    Business plan, lender package, term sheet.
    4 wk
    30 Dec 202627 Jan 2027
  5. Phase 5
    Manufacturing / fabrication
    Equipment build, panels, controls, FAT.
    13 wk
    27 Jan 202728 Apr 2027
  6. Phase 6
    Shipping & logistics
    Sea/air freight, customs, inland transport.
    5 wk
    28 Apr 202702 Jun 2027
  7. Phase 7
    Site preparation & civil works
    Foundations, floor, drainage, incoming utilities.
    8 wk
    02 Jun 202728 Jul 2027
  8. Phase 8
    Mechanical & electrical installation
    Envelope, refrigeration, piping, electrical, controls.
    9 wk
    28 Jul 202729 Sept 2027
  9. Phase 9
    Testing & SAT
    Site acceptance, pressure/leak, controls integration.
    3 wk
    29 Sept 202720 Oct 2027
  10. Phase 10
    Commissioning & handover
    Cool-down, training, documentation, warranty start.
    3 wk
    20 Oct 202710 Nov 2027
Direct answer

A realistic cold storage schedule has five phases: concept and specification (3–6 weeks), supplier selection and contracting (4–8 weeks), equipment manufacture and lead time (12–24 weeks), construction and installation (12–30 weeks, partly parallel), and commissioning plus temperature validation (4–8 weeks). Compressors and insulated panels are almost always the critical path.

Frequently asked questions

What has the longest lead time in a cold storage project?

Industrial compressors and screw packs at 12–24 weeks, followed by insulated panels and doors. Order these first.

How long is commissioning?

Four to eight weeks including pull-down, temperature mapping, alarm testing and documentation for certification.

Can construction and manufacturing overlap?

Yes — civil works and the envelope usually run in parallel with equipment manufacture, saving 2–4 months versus a sequential schedule.