Cold-chain project timeline generator

Enter a few project parameters — get an indicative phased schedule from feasibility to commissioning. For planning conversations with stakeholders, lenders and suppliers. Not a contractual schedule.

Indicative planning schedule only. Actual timelines depend on country, permitting, financing close, supplier lead times, logistics, site conditions and scope. Confirm milestones with your engineering & procurement team and suppliers.
Indicative schedule

Cold storage / refrigerated warehouse

Total duration
60 weeks
Handover ≈ 13 Sept 2027
  1. Phase 1
    Feasibility & site survey
    Concept, catchment / demand, site walk, utility check.
    4 wk
    20 Jul 202617 Aug 2026
  2. Phase 2
    Basic + detailed design
    FEED, layouts, load calculations, specifications.
    6 wk
    17 Aug 202628 Sept 2026
  3. Phase 3
    Supplier selection & PO
    RFQ, technical & commercial evaluation, contract.
    5 wk
    28 Sept 202602 Nov 2026
  4. Phase 4
    Financing preparation
    Business plan, lender package, term sheet.
    4 wk
    02 Nov 202630 Nov 2026
  5. Phase 5
    Manufacturing / fabrication
    Equipment build, panels, controls, FAT.
    13 wk
    30 Nov 202601 Mar 2027
  6. Phase 6
    Shipping & logistics
    Sea/air freight, customs, inland transport.
    5 wk
    01 Mar 202705 Apr 2027
  7. Phase 7
    Site preparation & civil works
    Foundations, floor, drainage, incoming utilities.
    8 wk
    05 Apr 202731 May 2027
  8. Phase 8
    Mechanical & electrical installation
    Envelope, refrigeration, piping, electrical, controls.
    9 wk
    31 May 202702 Aug 2027
  9. Phase 9
    Testing & SAT
    Site acceptance, pressure/leak, controls integration.
    3 wk
    02 Aug 202723 Aug 2027
  10. Phase 10
    Commissioning & handover
    Cool-down, training, documentation, warranty start.
    3 wk
    23 Aug 202713 Sept 2027