Cold-chain project timeline generator
Enter a few project parameters — get an indicative phased schedule from feasibility to commissioning. For planning conversations with stakeholders, lenders and suppliers. Not a contractual schedule.
Cold storage / refrigerated warehouse
- Phase 1Feasibility & site surveyConcept, catchment / demand, site walk, utility check.4 wk31 Oct 2026 → 28 Nov 2026
- Phase 2Basic + detailed designFEED, layouts, load calculations, specifications.6 wk28 Nov 2026 → 09 Jan 2027
- Phase 3Supplier selection & PORFQ, technical & commercial evaluation, contract.5 wk09 Jan 2027 → 13 Feb 2027
- Phase 4Financing preparationBusiness plan, lender package, term sheet.4 wk13 Feb 2027 → 13 Mar 2027
- Phase 5Manufacturing / fabricationEquipment build, panels, controls, FAT.13 wk13 Mar 2027 → 12 Jun 2027
- Phase 6Shipping & logisticsSea/air freight, customs, inland transport.5 wk12 Jun 2027 → 17 Jul 2027
- Phase 7Site preparation & civil worksFoundations, floor, drainage, incoming utilities.8 wk17 Jul 2027 → 11 Sept 2027
- Phase 8Mechanical & electrical installationEnvelope, refrigeration, piping, electrical, controls.9 wk11 Sept 2027 → 13 Nov 2027
- Phase 9Testing & SATSite acceptance, pressure/leak, controls integration.3 wk13 Nov 2027 → 04 Dec 2027
- Phase 10Commissioning & handoverCool-down, training, documentation, warranty start.3 wk04 Dec 2027 → 25 Dec 2027
A realistic cold storage schedule has five phases: concept and specification (3–6 weeks), supplier selection and contracting (4–8 weeks), equipment manufacture and lead time (12–24 weeks), construction and installation (12–30 weeks, partly parallel), and commissioning plus temperature validation (4–8 weeks). Compressors and insulated panels are almost always the critical path.
Frequently asked questions
What has the longest lead time in a cold storage project?
Industrial compressors and screw packs at 12–24 weeks, followed by insulated panels and doors. Order these first.
How long is commissioning?
Four to eight weeks including pull-down, temperature mapping, alarm testing and documentation for certification.
Can construction and manufacturing overlap?
Yes — civil works and the envelope usually run in parallel with equipment manufacture, saving 2–4 months versus a sequential schedule.
- Cold Storage Energy & Backup Power Guide
- Cold Storage Project Cost Center
- Cold Chain Project Financing Options
- All Cold Chain Buyer Guides
Send these inputs to an RFQ
Your size, cost and load inputs are copied into the quote form, so you don't type them twice. Nothing is sent until you review and submit.
Free for buyers, no obligation. These figures are estimates, not quotes — our team reviews your request and contacts suitable suppliers on your behalf.
Submit your project for expert review
Send your requirements. A ColdMatch specialist reviews every request, prepares a brief and introduces suitable suppliers — free for buyers.