Detailed RFQ guide

A detailed RFQ for industrial refrigeration — description, comparison matrix & completion date

A detailed RFQ is the single most effective way to get comparable, reliable proposals for an industrial refrigeration or cold-storage project. This guide explains what a complete RFQ contains, how to compare supplier proposals side by side, and how to plan a realistic timeline from brief to project completion. ColdMatch reviews every RFQ manually before any supplier research begins — the service is free for qualified buyers with projects of USD 250K or more.

What a detailed RFQ must describe

A strong refrigeration RFQ describes the facility, the product and the duty — not a pre-selected brand. Include the site location and climate conditions, the products stored and their incoming temperature, the required room temperature and humidity range, daily throughput and door-opening patterns, and the target storage capacity in tonnes or pallet positions.

Add the constraints that shape the design: available electrical supply, preferred refrigerant policy (for example natural refrigerants such as ammonia or CO2), noise limits, building dimensions or land available, and any food-safety or pharmaceutical compliance requirements (HACCP, GDP, local regulations).

Finally, state the commercial frame: budget range, target completion date, payment terms you can work with, and whether you need supply-only, supply-and-install, or a full turnkey EPC scope. The more complete the brief, the fewer assumptions each supplier has to make — and the more comparable the proposals become.

Why vague RFQs produce expensive quotes

When an RFQ leaves the duty undefined, every supplier sizes the system differently. One quotes for a heavier safety margin, another for the minimum duty, and a third assumes a different operating schedule. The prices look far apart, but the real difference is the scope hidden behind them.

A detailed RFQ removes that ambiguity. It lets each supplier price the same duty, the same operating profile and the same completion date — so the remaining differences are real differences in equipment, efficiency, warranty and service.

Comparison matrix

The supplier proposal comparison matrix

When proposals arrive, score each one against the same criteria. This matrix is the structure ColdMatch uses when preparing a buyer-side comparison.

CriterionWhat to checkWhy it matters
Cooling capacity (kW) at design conditionsRated duty at your actual ambient and room temperatures, not catalogue conditionsCapacity quoted at standard conditions can be 15–30% lower at a hot site
Energy efficiency (COP / kWh per year)Seasonal efficiency and estimated annual electricity consumptionElectricity is the largest operating cost over the system's life
Refrigerant and chargeRefrigerant type, charge size and compliance with local regulationAffects safety, permitting, maintenance cost and future regulation risk
Scope of supplyExactly what is included: panels, doors, racks, controls, installation, commissioningMissing scope items become expensive change orders later
Delivery and completion scheduleManufacturing lead time, shipping, installation weeks and the committed completion dateA cheap proposal with a late completion date can cost more in lost operation
Warranty and serviceWarranty length, response time, spare-parts availability and local service partnerDowntime in cold storage directly threatens the stored product
Total cost of ownershipPurchase price plus 10-year energy, maintenance and refrigerant costsThe lowest purchase price is rarely the lowest lifetime cost
References and track recordComparable completed projects in similar climate and applicationVerifiable references are the best predictor of a smooth project
Timeline to completion

From RFQ to completion date — a realistic timeline

  1. 01RFQ preparation1–2 weeks

    Define the duty, constraints and commercial frame. ColdMatch reviews the brief and helps close gaps before supplier research.

  2. 02Supplier research and shortlisting1–3 weeks

    Qualified suppliers are identified from a network of 100+ and introduced manually, matched to the project's technology and region.

  3. 03Proposal collection2–4 weeks

    Suppliers prepare proposals against the same brief. Clarification questions are answered once, for everyone.

  4. 04Comparison and negotiation1–2 weeks

    Proposals are compared in a structured matrix; scope and schedule are aligned before final selection.

  5. 05Manufacturing and delivery8–20 weeks

    Depends on equipment type and customization. Agreed milestones and the completion date are fixed in the contract.

  6. 06Installation and commissioning2–8 weeks

    Site works, system charging, performance testing and handover against the agreed duty.

Typical total timeline from a complete RFQ to commissioned facility: roughly 4–9 months for standard cold-storage projects; complex process-cooling or pharmaceutical facilities can take longer. Stating your target completion date in the RFQ lets suppliers commit to a realistic schedule instead of a generic one.