3,200 TR central HVAC district cooling plant serving a commercial complex in Doha, Qatar
HVAC & District Cooling

Central HVAC District Cooling Plant — Doha

Central chilled-water plant for a mixed-use development — 3,200 TR, high-efficiency centrifugal chillers, TES-ready.

Location
Doha, Qatar
Capacity
3,200 TR district cooling
Temperature
5.5 °C / 13 °C chilled water
Budget
USD $18M–$22M
Timeline
20 months

Project overview

A Qatari developer needed a central plant to serve retail, office and hospitality towers under a single ESCO-style operating model. ColdMatch Group sourced chillers, cooling towers, pumps, BMS and thermal energy storage provisioning through a competitive tender.

Challenge

  • Peak cooling demand coincided with peak electrical tariff windows.
  • Multiple end-users required transparent metering and SLA-based billing.
  • Plant footprint constrained by architectural masterplan.

Solution

  • High-efficiency water-cooled centrifugal chillers with variable-speed drives.
  • Space and interfaces provisioned for future TES tank to shift 20% of load off-peak.
  • BTU metering per tenant with BMS-integrated billing feed.

Result

  • IPLV of 0.42 kW/TR — 18% better than local benchmark.
  • TES-ready design provides estimated 12–15% OPEX reduction when phase 2 is added.
  • Zero occupant complaints in first cooling season.

Scope of works

  • Water-cooled centrifugal chillers, N+1
  • Cooling towers, primary and secondary pumps
  • BMS with analytics and BTU metering
  • TES provisioning (phase 2)
  • O&M plan and training

Project gallery

Water-cooled chillers with cooling towers
Water-cooled centrifugal chillers
BMS dashboard for district cooling optimisation
BMS + optimisation analytics
Preventive maintenance planning for HVAC equipment
5-year O&M plan