Worked project case study · Poland

Cold room project case study in Poland: Legacy plant replacement in a 1,800-pallet frozen store, Greater Poland

An HFC plant approaching end of life and facing refrigerant phase-down was replaced with a CO₂ system while the store stayed operational.

Direct answer

A 1,800-pallet −18 to −25 °c frozen facility in Poland of roughly 8,100 m³, built with co2 (r744) transcritical or cascade, models at about USD 4,926,566 installed (USD 3,941,253USD 6,404,536 planning range) and USD 788,262 a year to run, over a 52-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Food logistics operator
Product
Frozen ready meals and vegetables
Capacity
1,800 pallets · 8,100 m³
Temperature class
−18 to −25 °C frozen
Refrigeration system
CO2 (R744) transcritical or cascade
Site status
Retrofit inside operating facility
Design ambient
32 °C peak

Moderate humidity — standard defrost and condenser selection

Grid
Stable grid — backup sized for short interruptions

~30 generator hours modelled per year

Indicative tariff
0.150 USD/kWh

Local band 0.120–0.190 USD/kWh

Zones

  • Frozen store −22 °C, 1,800 pallets
  • Chilled dispatch dock +4 °C
  • New machine room adjacent to the existing plant room
Costs

What a project like this costs in Poland

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 4,926,566

Planning range USD 3,941,253–USD 6,404,536

CAPEX per pallet
USD 2,737

USD 608 per m³

Annual OPEX
USD 788,262

66% of it is energy

OPEX per pallet / year
USD 438

390 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 4,895,786
Monitoring and alarmsUSD 30,780
Total installedUSD 4,926,566
Annual OPEX breakdown
Grid electricity (3,417,054 kWh)USD 512,558
Standby diesel (2,785 litres)USD 4,038
Maintenance and sparesUSD 141,885
Operations labour (10 staff)USD 126,000
Monitoring and complianceUSD 3,780
Total per yearUSD 788,262

Running the same facility on legacy fixed-speed plant models at USD 1,059,160 a year — about USD 270,898 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Poland

These are the local realities that change the design, the price and the supplier shortlist.

  • Store cannot be emptied — changeover must be phased
  • F-gas phase-down makes HFC top-ups increasingly expensive
  • Energy price volatility makes efficiency the main business case
Engineering decisions

The decisions that shaped the result

  • New CO₂ plant built alongside, then cut over zone by zone
  • High-efficiency package with VSD and floating pressure control
  • Heat recovery to the office and dock heating circuits
Timeline

Programme: about 52 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Enabling works and shutdown planning

    Weeks 1421 · 8 weeks

    Condition survey, tie-in plan and shutdown windows agreed with operations so production is not interrupted.

  5. 5

    Equipment manufacture and delivery

    Weeks 2237 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 3847 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 4852 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • Refrigerant risk and phase-down exposure removed
  • Measured energy reduction against the legacy plant baseline
  • Cutover completed without emptying the store
Lessons

What buyers in this market should take from it

  • A phased cutover plan is worth more than a small price difference between bidders
  • Baseline the old plant's energy before cutover or you cannot prove the saving
Model your own numbers

Tools and market data for Poland

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Poland

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Poland?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.