Sandwich panels are the thermal envelope of every cold-storage facility. Core material, thickness and joint sealing decide long-term energy cost, fire compliance and insurance premiums.

Overview

What it is & where it's used

Prefabricated panels with metal skins (0.5–0.7 mm pre-painted steel or stainless) bonded to a rigid foam or mineral-wool core. Cam-lock and tongue-and-groove joints create a vapour-sealed envelope.

Where it's used
  • Cold rooms and frozen warehouses
  • Food processing walls and ceilings
  • Pharmaceutical clean rooms
  • Retail back-of-store
  • Industrial partitions
Typical applications
  • Chilled 0–5 °C (100–120 mm)
  • Frozen –18 to –25 °C (150–200 mm)
  • Blast –35 to –40 °C (200–250 mm)
  • Fire-rated separation walls
Benefits
  • Fast install — 1,000 m² per week per crew
  • Predictable thermal performance
  • Modular expansion and dismantling
  • Hygienic food-grade skin coatings
Limitations
  • Cheap panels lose 20–40% of U-value in 5 years
  • Joint sealing is 60% of installed performance
  • PUR/PIR fire behaviour requires certification for insurance

Typical project sizes: 40–250 mm thickness, 1,000–1,200 mm width, up to 20 m length.

Technology Comparison

PIR / PUR Foam Core vs Mineral-Wool Core

CriterionPIR / PUR Foam CoreMineral-Wool Core
U-value @ 100 mm0.22 W/m²K0.42 W/m²K
Thickness for –25 °C150–200 mm200–250 mm
Fire class (EN 13501)B-s2,d0 (PIR)A2-s1,d0 non-combustible
Density38–48 kg/m³100–120 kg/m³
Weight @ 100 mm10–14 kg/m²22–30 kg/m²
CAPEXBaseline+15–35%
Best forStandard cold and frozen roomsInsurer-mandated, high fire-risk zones
Buying Guide

How to evaluate

  • 01Specify U-value target (0.14–0.18 W/m²K for frozen; 0.22–0.27 for chilled).
  • 02Insist on EN 13501-1 fire certification — insurers now demand it.
  • 03Verify skin thickness ≥0.6 mm and coating (PVDF for coastal, food-grade for processing).
  • 04Reject panels with core density <38 kg/m³ — they age poorly.
  • 05Vapour barrier and joint sealing dominate lifetime performance — inspect installer references.
  • 06For food contact: specify HACCP-approved skin finish and antibacterial coating.
  • 07Confirm 10-year structural warranty and 5-year skin warranty.
Technical Specification

Spec checklist

  • Panel core material and density
  • Panel thickness and U-value
  • Skin material, thickness and coating
  • Fire class (A2 / B / F) and certification body
  • Cam-lock or tongue-and-groove joint
  • Vapour barrier method
  • Suspension load rating (ceiling panels)
  • Wind load rating (external walls)
  • Colour, RAL code and interior finish
  • Sealant type (silicone / PU / neutral cure)
Budget Guide

Investment & operating cost

Typical investment ranges
  • PIR 100 mm chilled panelUSD 45 – 75/m²
  • PIR 150–200 mm frozen panelUSD 75 – 120/m²
  • Mineral-wool 150 mm fire-ratedUSD 90 – 140/m²
  • Installed cold room (materials + labour)USD 250 – 650/m² floor area

Indicative ranges. Actual quotations vary by country, scope, spec, freight and site conditions.

Major cost drivers
  • Core material and thickness
  • Skin quality and coating
  • Fire class
  • Panel length (custom > standard)
  • Freight and installation labour
Optional equipment
  • Anti-microbial food-grade coating
  • Stainless AISI 304/316 skins
  • Cove profiles (hygienic)
  • Underfloor heating cables
Installation considerations
  • Level slab within ±3 mm/3 m
  • Vapour barrier under slab (frozen)
  • Panel-to-floor cove profile
  • Sealant application per joint
Operating cost
  • Standing losses 15–90 kWh/m²/year by temperature class
  • No consumables
Maintenance expectations
  • Annual joint sealant inspection
  • Skin repair after impact
  • Vapour barrier check every 5 years
Procurement Workflow

Before you request quotations

  • Define production goals and daily throughput (kg/day)
  • Confirm utilities: power (kVA), water, drainage, compressed air
  • Define project scope (turnkey vs supply-only vs hybrid)
  • Prepare site layout, floor plan and clear height
  • Confirm local regulations (F-Gas, ATEX, HACCP, seismic code)
  • Determine financing route (own cash, lease, bank loan, ECA)
  • Create technical specification with U-values and setpoints
  • Prepare RFQ and shortlist qualified international suppliers
Supplier Comparison

Interactive evaluation matrix

Score each shortlisted supplier on the criteria below. All calculations run locally — nothing is sent to our servers.

Supplier Evaluation Matrix
Criterion
Price / Investment
Turnkey CAPEX including installation, controls and commissioning.
Warranty (years)
Comprehensive, on major components (compressors, PLC, panels).
Lead time (weeks)
Ex-works or delivered to site including customs.
Energy efficiency (SEC / COP)
Lower SEC or higher COP is better.
Local service & spare parts
Response time, service partner in country, stocked spares.
References / installed base
Comparable capacity, region and application.
Maintenance program
Preventive maintenance plan, remote monitoring.
Operator training
On-site training days, documentation, language.
Expandability
Add capacity, modules or additional rooms later.
Lifecycle cost (10y)
CAPEX + energy + maintenance + refrigerant cost of ownership.
Total score0 / 500 / 500 / 50
Score each criterion 1 (weak) – 5 (excellent). Data stays in your browser. Use the printed matrix in your tender-evaluation meeting.
FAQ

Common questions

PIR or mineral wool?

PIR gives best U-value per mm and lowest CAPEX. Mineral wool is chosen where insurance or local fire code demands A2 non-combustible construction — typical in bakeries, oil kitchens and insurer-critical warehouses.

How thick should a chilled panel be?

100–120 mm PIR for 0–5 °C rooms delivers U ≈ 0.22–0.27 W/m²K and pays back thermally in most climates.

Why do cheap panels fail?

Under-density foam (<38 kg/m³) creeps and separates from skins within 3–5 years, degrading U-value by 20–40% and creating condensation risk.

Related tools & guides

Continue your planning

Planning a project?

Receive structured, comparable quotations from qualified international suppliers — vendor-neutral. Add financing pre-qualification if the project requires equipment leasing, project loan or ECA-backed facility.

Get Free QuotesFind the Best Solution