Worked project case study · Vietnam

Cold room project case study in Vietnam: IQF line and 1,200-pallet frozen store, Mekong Delta

A new export line needed IQF capacity matched to the processing rate, with energy cost per tonne kept competitive against regional rivals.

Direct answer

A 1,200-pallet −30 to −40 °c blast / deep frozen facility in Vietnam of roughly 5,500 m³, built with ammonia (r717) industrial plant, models at about USD 7,392,333 installed (USD 5,913,866USD 9,610,033 planning range) and USD 725,096 a year to run, over a 64-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Pangasius and shrimp exporter
Product
IQF fillets and value-added frozen seafood
Capacity
1,200 pallets · 5,500 m³
Temperature class
−30 to −40 °C blast / deep frozen
Refrigeration system
Ammonia (R717) industrial plant
Site status
New build including civil works
Design ambient
37 °C peak

Hot and humid — higher defrost energy and infiltration load

Grid
Occasional outages — standby generation strongly recommended

~260 generator hours modelled per year

Indicative tariff
0.080 USD/kWh

Local band 0.060–0.110 USD/kWh

Zones

  • IQF spiral freezer sized to line rate
  • Frozen store −22 °C, 1,200 pallets
  • Chilled processing hall +12 °C
Costs

What a project like this costs in Vietnam

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 7,392,333

Planning range USD 5,913,866–USD 9,610,033

CAPEX per pallet
USD 6,160

USD 1,344 per m³

Annual OPEX
USD 725,096

46% of it is energy

OPEX per pallet / year
USD 604

436 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 6,794,961
Standby generationUSD 577,572
Monitoring and alarmsUSD 19,800
Total installedUSD 7,392,333
Annual OPEX breakdown
Grid electricity (3,821,959 kWh)USD 305,757
Standby diesel (26,998 litres)USD 24,298
Maintenance and sparesUSD 201,071
Operations labour (16 staff)USD 190,400
Monitoring and complianceUSD 3,570
Total per yearUSD 725,096

Running the same facility on legacy fixed-speed plant models at USD 898,174 a year — about USD 173,078 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Vietnam

These are the local realities that change the design, the price and the supplier shortlist.

  • Humid climate raising defrost demand
  • Buyer audits on hygiene, traceability and social compliance
  • Energy cost per tonne is a direct competitiveness factor
Engineering decisions

The decisions that shaped the result

  • Two-stage ammonia plant with VSD compressors and floating suction pressure
  • Freezer capacity matched to the packing line, avoiding an expensive idle machine
  • Sub-metering per zone from day one
Timeline

Programme: about 64 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Civil works and building envelope

    Weeks 1433 · 20 weeks

    Slab, drainage, docks and structure, including under-floor heating detail where freezer rooms sit on grade.

  5. 5

    Equipment manufacture and delivery

    Weeks 3449 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 5059 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 6064 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • Freezing capacity aligned with the line rather than oversized
  • Energy per tonne frozen tracked and benchmarked monthly
  • Audit documentation prepared before the first export shipment
Lessons

What buyers in this market should take from it

  • Oversized freezers waste both CAPEX and energy — size on line rate
  • Sub-metering is cheap at build and impossible to retrofit fairly
Model your own numbers

Tools and market data for Vietnam

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Vietnam

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Vietnam?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.