Worked project case study · Indonesia

Cold room project case study in Indonesia: Island landing-site cold store and ice plant, Eastern Indonesia

Fish quality was lost between landing and the mainland. A modest, robust cold store with ice production was built at the landing site rather than a large plant far away.

Direct answer

A 500-pallet −18 to −25 °c frozen facility in Indonesia of roughly 2,400 m³, built with packaged / condensing units (hfc-hfo), models at about USD 2,248,399 installed (USD 1,798,719USD 2,922,919 planning range) and USD 353,292 a year to run, over a 70-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Fisheries cooperative and processing partner
Product
Tuna and reef fish for domestic and export markets
Capacity
500 pallets · 2,400 m³
Temperature class
−18 to −25 °C frozen
Refrigeration system
Packaged / condensing units (HFC-HFO)
Site status
New build including civil works
Design ambient
34 °C peak

Hot and humid — higher defrost energy and infiltration load

Grid
Frequent outages — continuous standby generation is a design requirement

~900 generator hours modelled per year

Indicative tariff
0.090 USD/kWh

Local band 0.070–0.120 USD/kWh

Zones

  • Frozen store −20 °C, 500 pallets
  • Chilled holding room 0 to +2 °C
  • Flake ice plant with insulated ice store
Costs

What a project like this costs in Indonesia

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 2,248,399

Planning range USD 1,798,719–USD 2,922,919

CAPEX per pallet
USD 4,497

USD 937 per m³

Annual OPEX
USD 353,292

43% of it is energy

OPEX per pallet / year
USD 707

158 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 2,015,898
Standby generationUSD 221,749
Monitoring and alarmsUSD 10,752
Total installedUSD 2,248,399
Annual OPEX breakdown
Grid electricity (1,381,249 kWh)USD 124,312
Standby diesel (33,774 litres)USD 28,708
Maintenance and sparesUSD 82,741
Operations labour (7 staff)USD 112,700
Monitoring and complianceUSD 4,830
Total per yearUSD 353,292

Running the same facility on legacy fixed-speed plant models at USD 391,547 a year — about USD 38,255 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Indonesia

These are the local realities that change the design, the price and the supplier shortlist.

  • Weak local grid and expensive logistics for spare parts
  • Coastal corrosion and limited technician availability
  • Shipping equipment to the island adds cost and lead time
Engineering decisions

The decisions that shaped the result

  • Packaged, standardised units so any competent technician can service them
  • Full-load generator with fuel storage as the primary design case
  • Commissioning package including local operator training
Timeline

Programme: about 70 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Civil works and building envelope

    Weeks 1433 · 20 weeks

    Slab, drainage, docks and structure, including under-floor heating detail where freezer rooms sit on grade.

  5. 5

    Equipment manufacture and delivery

    Weeks 3455 · 22 weeks

    Plant and panel manufacture plus extended shipping, customs clearance and inland transport — the schedule risk to watch in this market.

  6. 6

    Installation and insulation

    Weeks 5665 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 6670 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • First-mile chilling and freezing available at the landing site
  • Ice availability removed the main quality-loss point
  • Local operators trained to run and basic-service the plant
Lessons

What buyers in this market should take from it

  • On remote sites, choose equipment you can repair, not equipment with the best datasheet
  • Budget freight and installation logistics as a separate CAPEX line
Model your own numbers

Tools and market data for Indonesia

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Indonesia

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Indonesia?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.