Worked project case study · Peru

Cold room project case study in Peru: Mixed fruit and seafood cold store, Callao / Chincha corridor

Two seasonal businesses shared one site. The design allowed fruit pre-cooling capacity to be redeployed to frozen seafood outside the harvest window.

Direct answer

A 1,050-pallet +2 to +8 °c chilled facility in Peru of roughly 5,000 m³, built with central plant, multi-compressor, models at about USD 2,889,060 installed (USD 2,311,248USD 3,755,777 planning range) and USD 353,518 a year to run, over a 63-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Agro-export and fisheries group
Product
Table grapes, blueberries and frozen seafood
Capacity
1,050 pallets · 5,000 m³
Temperature class
+2 to +8 °C chilled
Refrigeration system
Central plant, multi-compressor
Site status
New build including civil works
Design ambient
30 °C peak

Coastal / salt-laden air — corrosion-resistant condensers required

Grid
Occasional outages — standby generation strongly recommended

~220 generator hours modelled per year

Indicative tariff
0.100 USD/kWh

Local band 0.080–0.130 USD/kWh

Zones

  • Pre-cooling tunnels for grapes and berries
  • Chilled store 0 to +2 °C, 750 pallets
  • Frozen store −20 °C, 300 pallets for seafood
Costs

What a project like this costs in Peru

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 2,889,060

Planning range USD 2,311,248–USD 3,755,777

CAPEX per pallet
USD 2,751

USD 578 per m³

Annual OPEX
USD 353,518

33% of it is energy

OPEX per pallet / year
USD 337

125 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 2,644,295
Standby generationUSD 224,765
Monitoring and alarmsUSD 20,000
Total installedUSD 2,889,060
Annual OPEX breakdown
Grid electricity (1,093,520 kWh)USD 109,352
Standby diesel (6,536 litres)USD 7,517
Maintenance and sparesUSD 92,450
Operations labour (10 staff)USD 140,000
Monitoring and complianceUSD 4,200
Total per yearUSD 353,518

Running the same facility on legacy fixed-speed plant models at USD 414,803 a year — about USD 61,285 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Peru

These are the local realities that change the design, the price and the supplier shortlist.

  • Strong seasonality — idle plant for part of the year is wasted capital
  • Coastal humidity and salt exposure
  • Export buyers require pallet-level temperature records
Engineering decisions

The decisions that shaped the result

  • Shared central plant with zone valves so capacity follows the season
  • Separate suction group for the frozen zone
  • Pallet-level logging integrated with the WMS
Timeline

Programme: about 63 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Civil works and building envelope

    Weeks 1433 · 20 weeks

    Slab, drainage, docks and structure, including under-floor heating detail where freezer rooms sit on grade.

  5. 5

    Equipment manufacture and delivery

    Weeks 3449 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 5059 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 6063 · 4 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • Plant utilisation spread across the year instead of peaking twice
  • Fruit pre-cooling times met the exporter specification
  • One maintenance contract covering both product streams
Lessons

What buyers in this market should take from it

  • Seasonal businesses should size the plant on the combined annual profile, not one crop
  • Zone valving is cheap at design stage and impossible to add later
Model your own numbers

Tools and market data for Peru

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Peru

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Peru?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.