Worked project case study · Canada

Cold room project case study in Canada: 2,400-pallet frozen and chilled logistics facility, Ontario

A new 3PL facility designed for extreme seasonal swing, with dock and floor detailing given as much attention as the refrigeration plant.

Direct answer

A 2,400-pallet −18 to −25 °c frozen facility in Canada of roughly 10,800 m³, built with ammonia (r717) industrial plant, models at about USD 11,569,735 installed (USD 9,255,788USD 15,040,655 planning range) and USD 1,005,494 a year to run, over a 64-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Third-party logistics provider
Product
Frozen and chilled food distribution
Capacity
2,400 pallets · 10,800 m³
Temperature class
−18 to −25 °C frozen
Refrigeration system
Ammonia (R717) industrial plant
Site status
New build including civil works
Design ambient
31 °C peak

Dry / arid — low defrost load, high condensing temperatures

Grid
Stable grid — backup sized for short interruptions

~25 generator hours modelled per year

Indicative tariff
0.080 USD/kWh

Local band 0.060–0.120 USD/kWh

Zones

  • Frozen store −23 °C, 1,700 pallets
  • Chilled store +2 °C, 700 pallets
  • Heated dock with levellers and seals
Costs

What a project like this costs in Canada

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 11,569,735

Planning range USD 9,255,788–USD 15,040,655

CAPEX per pallet
USD 4,821

USD 1,071 per m³

Annual OPEX
USD 1,005,494

31% of it is energy

OPEX per pallet / year
USD 419

438 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 10,763,580
Standby generationUSD 753,451
Monitoring and alarmsUSD 52,704
Total installedUSD 11,569,735
Annual OPEX breakdown
Grid electricity (3,836,974 kWh)USD 306,958
Standby diesel (2,606 litres)USD 2,997
Maintenance and sparesUSD 462,789
Operations labour (13 staff)USD 227,500
Monitoring and complianceUSD 5,250
Total per yearUSD 1,005,494

Running the same facility on legacy fixed-speed plant models at USD 1,168,032 a year — about USD 162,537 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Canada

These are the local realities that change the design, the price and the supplier shortlist.

  • Deep winter and warm humid summer in one design envelope
  • Freezer floor heave risk requires under-floor heating
  • Client mix changes — zones must be re-purposable
Engineering decisions

The decisions that shaped the result

  • Under-floor heating and monitoring designed in, not value-engineered out
  • Ammonia plant with winter head-pressure control to exploit cold ambient
  • Zone flexibility so chilled space can be converted to frozen later
Timeline

Programme: about 64 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Civil works and building envelope

    Weeks 1433 · 20 weeks

    Slab, drainage, docks and structure, including under-floor heating detail where freezer rooms sit on grade.

  5. 5

    Equipment manufacture and delivery

    Weeks 3449 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 5059 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 6064 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • Winter operation exploited for genuine energy savings
  • Floor heave risk eliminated by design
  • Facility able to follow client mix changes without rebuild
Lessons

What buyers in this market should take from it

  • Under-floor heating is not optional in freezer new-builds in cold climates
  • Design zone convertibility on day one if you serve 3PL clients
Model your own numbers

Tools and market data for Canada

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Canada

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Canada?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.