Project Intelligence

Cold Chain Master Planner

Toggle the nodes of your cold chain network and get an indicative CAPEX split, phased roadmap and recommended procurement sequence. Independent, supplier-neutral planning.

CAPEX allocation (base)

$5.0M – $20.0M
NodeShareCAPEX range
Processing Plant35%$1.75M – $7.02M
Central Cold Storage44%$2.19M – $8.77M
Distribution Centers21%$1.05M – $4.21M

Recommended roadmap

  1. 1
    Phase 1 — Anchor site0–14 months
    Processing plant · Central cold storage
  2. 2
    Phase 2 — Distribution backbone10–22 months
    Distribution centers
Direct answer

A cold chain master plan sequences site, power, envelope, refrigeration and commissioning across a realistic timeline. For a mid-size facility (3,000–8,000 m³), budget 3–6 months for design and permits, 4–8 months for construction and equipment lead time, and 4–8 weeks for commissioning and temperature validation — 12–20 months total from decision to operation.

Frequently asked questions

How long does a cold storage project take end to end?

Typically 12–20 months for a mid-size facility: 3–6 months design and permitting, 4–8 months build and equipment delivery, 4–8 weeks commissioning and validation.

What is the most common cause of delay?

Grid power connection and permits. Both sit outside the contractor's control and should be started before equipment is ordered.

When should suppliers be engaged?

During concept design. Compressor and panel lead times of 12–24 weeks mean supplier selection drives the critical path more than construction does.