Worked project case study · France

Cold room project case study in France: GDP-compliant pharma store plus chilled food zone, Lyon region

A GDP-compliant pharmaceutical storage zone was created inside an existing chilled facility, with qualification and mapping delivered as part of the supply contract.

Direct answer

A 1,050-pallet +2 to +8 °c chilled facility in France of roughly 4,800 m³, built with central plant, multi-compressor, models at about USD 2,292,652 installed (USD 1,834,121USD 2,980,447 planning range) and USD 432,773 a year to run, over a 52-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Healthcare and food logistics operator
Product
+2 to +8 °C pharmaceuticals and chilled food
Capacity
1,050 pallets · 4,800 m³
Temperature class
+2 to +8 °C chilled
Refrigeration system
Central plant, multi-compressor
Site status
Existing building / shell available
Design ambient
34 °C peak

Moderate humidity — standard defrost and condenser selection

Grid
Stable grid — backup sized for short interruptions

~20 generator hours modelled per year

Indicative tariff
0.150 USD/kWh

Local band 0.120–0.200 USD/kWh

Zones

  • GDP pharma store +2 to +8 °C, 500 pallets, fully mapped
  • Chilled food store +2 to +4 °C, 450 pallets
  • Controlled dispatch airlock
Costs

What a project like this costs in France

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 2,292,652

Planning range USD 1,834,121–USD 2,980,447

CAPEX per pallet
USD 2,183

USD 478 per m³

Annual OPEX
USD 432,773

37% of it is energy

OPEX per pallet / year
USD 412

121 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 2,121,132
Standby generationUSD 148,479
Monitoring and alarmsUSD 23,040
Total installedUSD 2,292,652
Annual OPEX breakdown
Grid electricity (1,057,003 kWh)USD 158,550
Standby diesel (574 litres)USD 976
Maintenance and sparesUSD 86,571
Operations labour (11 staff)USD 181,720
Monitoring and complianceUSD 4,956
Total per yearUSD 432,773

Running the same facility on legacy fixed-speed plant models at USD 516,428 a year — about USD 83,654 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in France

These are the local realities that change the design, the price and the supplier shortlist.

  • GDP requires qualification, mapping, alarms and documented deviations
  • Existing building imposes layout and plant-room limits
  • High electricity price rewards efficiency investment
Engineering decisions

The decisions that shaped the result

  • N+1 refrigeration on the pharma zone with independent monitoring
  • IQ/OQ/PQ and mapping written into the supplier scope with acceptance criteria
  • Deviation workflow agreed with the quality team before go-live
Timeline

Programme: about 52 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Building preparation

    Weeks 1418 · 5 weeks

    Shell repairs, floor preparation, electrical upgrade and dock modifications inside the existing building.

  5. 5

    Equipment manufacture and delivery

    Weeks 1934 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 3544 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 4548 · 4 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

  8. 8

    Qualification and mapping

    Weeks 4952 · 4 weeks

    IQ/OQ/PQ, temperature mapping in loaded and empty conditions, alarm testing and the documentation pack required for audits.

Outcomes

What the project delivered

  • GDP zone qualified and released with a complete documentation pack
  • Food and pharma operations separated without a second building
  • Alarm escalation tested and documented at handover
Lessons

What buyers in this market should take from it

  • Qualification is a deliverable with acceptance criteria — never a promise
  • Ask who signs the mapping report before you sign the contract
Model your own numbers

Tools and market data for France

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in France

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in France?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Get Free QuotesFind the Best Solution