Worked project case study · Ecuador

Cold room project case study in Ecuador: IQF shrimp freezing line and frozen store, Guayaquil

Export growth outstripped the existing plate freezers. An IQF line was retrofitted into an operating plant without stopping production, then tied into an expanded frozen store.

Direct answer

A 950-pallet −30 to −40 °c blast / deep frozen facility in Ecuador of roughly 4,600 m³, built with ammonia (r717) industrial plant, models at about USD 5,295,412 installed (USD 4,236,329USD 6,884,035 planning range) and USD 659,753 a year to run, over a 52-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Shrimp exporter serving the EU, US and Asian markets
Product
IQF and block-frozen shrimp
Capacity
950 pallets · 4,600 m³
Temperature class
−30 to −40 °C blast / deep frozen
Refrigeration system
Ammonia (R717) industrial plant
Site status
Retrofit inside operating facility
Design ambient
33 °C peak

Hot and humid — higher defrost energy and infiltration load

Grid
Occasional outages — standby generation strongly recommended

~260 generator hours modelled per year

Indicative tariff
0.090 USD/kWh

Local band 0.070–0.120 USD/kWh

Zones

  • IQF spiral freezer, −35 °C air, continuous line
  • Frozen store −25 °C, 950 pallets
  • Chilled processing hall +10 °C
Costs

What a project like this costs in Ecuador

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 5,295,412

Planning range USD 4,236,329–USD 6,884,035

CAPEX per pallet
USD 5,574

USD 1,151 per m³

Annual OPEX
USD 659,753

42% of it is energy

OPEX per pallet / year
USD 694

336 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 4,863,605
Standby generationUSD 413,406
Monitoring and alarmsUSD 18,400
Total installedUSD 5,295,412
Annual OPEX breakdown
Grid electricity (2,940,824 kWh)USD 264,674
Standby diesel (20,774 litres)USD 11,426
Maintenance and sparesUSD 169,453
Operations labour (15 staff)USD 210,000
Monitoring and complianceUSD 4,200
Total per yearUSD 659,753

Running the same facility on legacy fixed-speed plant models at USD 804,537 a year — about USD 144,784 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Ecuador

These are the local realities that change the design, the price and the supplier shortlist.

  • Retrofit inside a running plant — tie-ins had to happen in scheduled shutdowns
  • Hot and humid ambient; defrost strategy is a real energy line
  • Buyer audits require hygienic design and traceable freezing records
Engineering decisions

The decisions that shaped the result

  • Ammonia plant extension rather than a separate packaged system, keeping one operator competency
  • Sequenced hot-gas defrost to avoid simultaneous demand peaks
  • Phased tie-in plan agreed with the supplier before contract award
Timeline

Programme: about 52 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Enabling works and shutdown planning

    Weeks 1421 · 8 weeks

    Condition survey, tie-in plan and shutdown windows agreed with operations so production is not interrupted.

  5. 5

    Equipment manufacture and delivery

    Weeks 2237 · 16 weeks

    Plant and panel manufacture with delivery sequenced to the installation programme.

  6. 6

    Installation and insulation

    Weeks 3847 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 4852 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • IQF throughput added without a production stop longer than a planned weekend
  • Freezing time per batch reduced versus the legacy plate freezers
  • Product quality claims supported by continuous line records
Lessons

What buyers in this market should take from it

  • In a retrofit, the shutdown plan is part of the technical bid — score it
  • Ask every bidder for defrost energy assumptions in writing
Model your own numbers

Tools and market data for Ecuador

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Ecuador

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Ecuador?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Get Free QuotesFind the Best Solution