Worked project case study · Nigeria

Cold room project case study in Nigeria: 1,400-pallet frozen and chilled distribution store, Lagos mainland

The buyer was renting third-party frozen space at rising monthly rates and losing product to grid failures. The project converted an existing warehouse shell into an own-operated frozen and chilled distribution store with full standby generation.

Direct answer

A 1,400-pallet −18 to −25 °c frozen facility in Nigeria of roughly 6,300 m³, built with central plant, multi-compressor, models at about USD 4,286,157 installed (USD 3,428,926USD 5,572,004 planning range) and USD 973,712 a year to run, over a 55-week programme from brief to handover. Figures are indicative planning estimates from ColdMatch Group's country cost model — not a quotation.

Human Global Expert GuidanceVendor-Neutral ProcurementQualified International SuppliersCommercial Confidentiality

A senior cold-chain specialist stays with your project from first brief to commissioning.

Project profile

What was built, and for whom

Buyer
Food distribution group supplying supermarkets and QSR chains
Product
Frozen poultry, fish and imported dairy
Capacity
1,400 pallets · 6,300 m³
Temperature class
−18 to −25 °C frozen
Refrigeration system
Central plant, multi-compressor
Site status
Existing building / shell available
Design ambient
38 °C peak

Hot and humid — higher defrost energy and infiltration load

Grid
Frequent outages — continuous standby generation is a design requirement

~1400 generator hours modelled per year

Indicative tariff
0.170 USD/kWh

Local band 0.120–0.240 USD/kWh

Zones

  • Main frozen store −22 °C, 1,100 pallets
  • Chilled buffer +2 °C, 300 pallets
  • Temperature-controlled dispatch dock +8 °C with dock shelters
Costs

What a project like this costs in Nigeria

Derived from the same indicative country cost model used by the public ColdMatch calculators: local construction cost index, design ambient, humidity, grid reliability, diesel price and electricity tariff. Planning-grade estimates, never a quotation.

Installed CAPEX
USD 4,286,157

Planning range USD 3,428,926–USD 5,572,004

CAPEX per pallet
USD 3,062

USD 680 per m³

Annual OPEX
USD 973,712

71% of it is energy

OPEX per pallet / year
USD 696

377 kW average refrigeration load

CAPEX breakdown
Envelope, plant, electrical and installationUSD 3,836,430
Standby generationUSD 422,007
Monitoring and alarmsUSD 27,720
Total installedUSD 4,286,157
Annual OPEX breakdown
Grid electricity (3,300,909 kWh)USD 561,155
Standby diesel (125,555 litres)USD 131,833
Maintenance and sparesUSD 144,015
Operations labour (9 staff)USD 132,300
Monitoring and complianceUSD 4,410
Total per yearUSD 973,712

Running the same facility on legacy fixed-speed plant models at USD 1,337,108 a year — about USD 363,396 more, which is the efficiency decision this project turned on.

Constraints

What made this project difficult in Nigeria

These are the local realities that change the design, the price and the supplier shortlist.

  • Grid supply unreliable — plant must run continuously on generator during outages
  • Hot and humid ambient drives defrost energy and condenser sizing
  • Import lead times for compressors and panels add months to the schedule
  • Diesel is a real second energy line, not a rounding error
Engineering decisions

The decisions that shaped the result

  • Central multi-compressor plant with N+1 rather than a bank of packaged units, so a single failure cannot stop dispatch
  • Generator sized for full refrigeration load plus dock lighting, with automatic transfer
  • High-efficiency plant with VSD and floating head pressure to reduce both grid and diesel consumption
Timeline

Programme: about 55 weeks from brief to handover

Phases overlap in practice. This sequence shows where the schedule risk sits in this market.

  1. 1

    Brief and feasibility

    Weeks 13 · 3 weeks

    Product, temperature, capacity, site status, electrical supply, budget band and timeline confirmed. ColdMatch reviews the brief and flags missing data before anyone is approached.

  2. 2

    Concept design and RFQ preparation

    Weeks 47 · 4 weeks

    Zone layout, load estimate, system shortlist and a single bid form so every supplier quotes identical scope, exclusions and assumptions.

  3. 3

    Supplier review and tendering

    Weeks 813 · 6 weeks

    Suitable suppliers are approached only after internal approval, then proposals are normalised on scope, energy assumptions, spares, commissioning and warranty.

  4. 4

    Building preparation

    Weeks 1418 · 5 weeks

    Shell repairs, floor preparation, electrical upgrade and dock modifications inside the existing building.

  5. 5

    Equipment manufacture and delivery

    Weeks 1940 · 22 weeks

    Plant and panel manufacture plus extended shipping, customs clearance and inland transport — the schedule risk to watch in this market.

  6. 6

    Installation and insulation

    Weeks 4150 · 10 weeks

    Panel erection, refrigeration pipework, electrical installation and controls.

  7. 7

    Commissioning, pull-down and handover

    Weeks 5155 · 5 weeks

    Leak and pressure testing, staged pull-down, performance verification against the specified duty, operator training, spares handover and documentation.

Outcomes

What the project delivered

  • Third-party storage rental eliminated; product loss from outages removed from the P&L
  • Dispatch capacity roughly tripled versus the rented space
  • Continuous temperature logging gave the buyer evidence for supermarket audits
Lessons

What buyers in this market should take from it

  • In Nigeria the standby power decision dominates both CAPEX and OPEX — price it before comparing suppliers
  • Insist every bidder quotes the same defrost strategy or the energy numbers are not comparable
Model your own numbers

Tools and market data for Nigeria

Change the capacity, temperature and system and the numbers above move. These tools use the same country model.

FAQ

Cold storage project costs and timelines in Nigeria

How ColdMatch Group works — independent B2B procurement and sourcing platform ColdMatch Group is an independent B2B procurement and sourcing platform for industrial refrigeration, cold storage and cold-chain projects from USD $250K+, connecting buyers with qualified third-party suppliers, EPC contractors and independent financing providers.

Have a comparable project in Nigeria?

Submit your product type, temperatures, capacity, site status, power situation, budget band and timeline. David and the ColdMatch team review the brief, structure the RFQ so every supplier quotes the same scope, and approach suitable suppliers only after internal approval.

This is a worked project example built from ColdMatch Group's indicative country cost model — local electricity tariff, design ambient, humidity, grid reliability and construction cost index. It is a planning-grade illustration, not a client transaction, an engineering design or a quotation. Supplier and manufacturer listings on this site are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

Get Free QuotesFind the Best Solution