Project Intelligence

Build vs Buy Analysis

Decide between building a new cold storage facility and acquiring/retrofitting an existing one. Model CAPEX, time-to-revenue, risk and expansion optionality — with Optimistic / Base / Pessimistic scenarios.

Build new (greenfield)

Buy existing + retrofit

Scenario:

Build new

Total CAPEX
$8.00M
Time to revenue
18 months
Key risk
Construction risk, permitting, weather delays. Highest scope-drift exposure.
Upside
Fit-for-purpose design, latest refrigerant, warranty from day one, easy to expand.

Buy + retrofit

Fastest to revenue
Total CAPEX
$8.30M
Time to revenue
6 months
Key risk
Hidden defects, refrigerant obsolescence (F-Gas / R-22 residual), locked layout.
Upside
Faster to revenue, existing certifications, brownfield financing familiar to banks.

Decision heuristic (not financial advice)

  • Time-to-revenue < 9 months critical → lean Buy.
  • Design must support ASRS, transcritical CO₂ or GDP pharma → lean Build.
  • Bank/ECA is unfamiliar with your market → Buy (brownfield) often finances faster.
  • Facility must scale 2–3x in 5 years → Build with modular expansion joints.
Direct answer

Building your own cold store makes financial sense when you need stable, long-term capacity: owned facilities typically cost USD 900–2,000 per m³ to build but only USD 25–60 per pallet per month to operate, versus USD 15–35 per pallet per month for 3PL rental with no CAPEX. As a rule of thumb, above roughly 70–80% sustained utilisation over 5+ years, owning beats renting; below that, 3PL is cheaper and far more flexible.

Frequently asked questions

When is renting 3PL cold storage cheaper than building?

When utilisation is seasonal or below about 70%, or when the horizon is under five years. You pay only for the pallets you use and avoid CAPEX, permits and maintenance.

What CAPEX should I budget to build a cold store?

Roughly USD 900–1,400 per m³ for chilled and USD 1,300–2,000 per m³ for frozen, including envelope, refrigeration, racking and installation. Land, power connection and permits are extra.

What hidden costs appear in the build option?

Grid connection upgrades, backup power, commissioning, spare parts stock, maintenance contracts, and 1.5–3% of CAPEX per year in ongoing servicing.

Next steps for your project
Get Free QuotesFind the Best Solution