← Case studies

Solar off-grid horticulture cold hub — Kenya

Horticulture exporter cooperative built a fully solar-powered cold hub with battery + thermal storage for flowers, avocado and French bean exports to EU markets — no grid connection.

Naivasha, Kenya 3,200 m² · 4,500 pallet positions +2 °C chill, −5 °C freeze 16 months, feasibility to community operation

Challenge

  • Grid extension quoted at US$ 2.1M with 30-month lead time.
  • Post-harvest losses at 22% due to lack of forced-air pre-cooling.
  • EU GlobalG.A.P. and cold-chain audit requirements from buyers.

ColdMatch solution

  • 1.6 MWp PV + 3.2 MWh Li-ion BESS + 1.4 MWh ice-bank thermal storage.
  • Low-charge NH₃/glycol plant (95 kg NH₃) + 4 forced-air pre-cooling tunnels.
  • Diesel genset (N+1, 400 kVA) for <3% annual runtime backup only.
  • ColdMatch structured GCF + AfDB green finance blended with cooperative equity.

Project scope

  • Civil: 3,200 m² insulated envelope, 4 pre-cooling tunnels, dock-level loading.
  • Mechanical: low-charge NH₃/glycol plant 620 kW, 4× forced-air tunnels @ 20 t/hr.
  • Solar/storage: 1.6 MWp bifacial PV, 3.2 MWh Li-ion BESS, 1.4 MWh ice-bank.
  • Automation: SCADA + energy management, remote monitoring via GSM.
  • Financing: GCF concessional + AfDB senior + cooperative equity — 10-yr tenor.

Key engineering metrics

Cooling load
620 kW peak
Solar fraction (annual)
94%
Diesel runtime
<3% / yr
Pre-cool throughput
80 t/hr aggregate
Refrigerant charge
95 kg NH₃ (low-charge)
Post-harvest loss
22% → 6%

ROI & financial performance

Capex
US$ 6.8M
Annual savings
US$ 2.1M/yr (loss reduction + no diesel + export uplift)
Payback
3.6 yrs
IRR
26.2% (10-yr)
NPV
US$ 7.4M @ 9% WACC
Energy reduction
94% grid-free (solar fraction)
CO₂ reduction
−1,850 t CO₂e/yr vs diesel BAU
We skipped the grid connection entirely. Payback under four years and post-harvest loss down from 22% to 6%.
Chair, horticulture cooperative
End-to-end delivery

How this project was delivered — planning to commissioning

Donor-supported off-grid delivery with local operator training. Total programme: 16 months, feasibility to community operation.

  1. 1

    Planning & feasibility

    Months 1–4
    • Harvest-volume and post-harvest-loss study across the catchment area.
    • Solar resource assessment, load profiling and thermal-battery sizing.
    • Affordability model built around farmer tariffs and grant funding.

    Milestone: Feasibility case approved and funding committed.

  2. 2

    Permitting & approvals

    Months 4–7
    • County land allocation and community consent secured.
    • Energy regulator notification for the off-grid generation asset.
    • Food handling and produce aggregation registration completed.

    Milestone: Land, energy and food-handling approvals issued.

  3. 3

    Procurement & build-out

    Months 7–13
    • Solar array, inverters, battery and thermal storage installed.
    • Cold rooms and aggregation area constructed with high-spec insulation.
    • Remote monitoring installed for off-grid performance visibility.

    Milestone: Hub built and running on solar with storage backup.

  4. 4

    Testing & validation

    Months 13–15
    • Autonomy testing across consecutive low-irradiance days.
    • Temperature stability verified through full load and door-cycle conditions.
    • Loss-reduction measured against the pre-project produce baseline.

    Milestone: Autonomy and loss-reduction targets confirmed in field conditions.

  5. 5

    Commissioning & handover

    Months 15–16
    • Local operator and cooperative training on daily operation and basic maintenance.
    • Tariff collection, booking and stock-rotation processes launched.
    • Remote support and spares channel established for the region.

    Milestone: Hub handed to the cooperative under a supported operating model.

Planning the same project?

This project sits under the Improve Energy Efficiency objective. Start from the objective hub to scope capacity, permitting and budget before engaging suppliers.

Procurement record

Project brief → RFQ package → supplier outreach → outcome

Every ColdMatch project follows the same managed sequence. Nothing reaches a supplier before David has reviewed the brief and confirmed the project scope, budget and timeline.

1. Project brief 2. RFQ package 3. Managed supplier outreach 4. Commercial outcome

1. Project brief

Submitted via
RFQ builder — off-grid horticulture cold hub
Review
Reviewed manually by David with the green-finance workstream

Clarified before outreach

  • Grid alternative: US$ 2.1M extension quote with a 30-month lead time.
  • Post-harvest loss baseline and the pre-cooling capacity needed to remove it.
  • Buyer audit requirements (GlobalG.A.P. and EU cold-chain evidence).

Qualification checks

  • Blended concessional and senior debt structure confirmed as feasible.
  • Cooperative governance and a single accountable project lead.
  • Export offtake volumes evidenced before supplier contact.

2. RFQ package issued

Integrated energy-and-refrigeration tender (no split award)

Documents in the pack

  • Forced-air pre-cooling brief: 4 tunnels at 20 t/hr, product entry temperatures.
  • Off-grid energy brief: PV, BESS, ice-bank and genset runtime ceiling.
  • Low-charge ammonia requirement with a safety and training plan.
  • Concessional-finance reporting and monitoring obligations.

Mandatory supplier returns

  • Annual energy simulation proving <3% genset runtime.
  • Guaranteed pre-cooling rate at design ambient.
  • Local operator training and remote-monitoring plan.
  • Ten-year service and spares proposal matching the loan tenor.

3. Managed supplier outreach

Approached
8 suppliers screened across East Africa, Europe and India
Shortlisted
3 progressed to tender as integrated energy + refrigeration bids
  1. Round 1 — off-grid capability

    Suppliers without proven off-grid cold-chain references were excluded early.

  2. Round 2 — integrated tender

    Energy and refrigeration bid as one package so no party could blame the other for shortfalls.

  3. Round 3 — finance alignment

    Monitoring, reporting and training obligations written into the supply contract.

Evaluation weighting

Off-grid energy performance
30%
Pre-cooling capacity & product quality
30%
Local service & training
20%
Price (normalised scope)
20%

4. Commercial outcome

1.6 MWp PV with BESS and ice-bank, paired with a 95 kg low-charge NH₃/glycol plant

Delivered results

  • Grid extension avoided, removing a 30-month delay.
  • Post-harvest losses cut from a 22% baseline through forced-air pre-cooling.
  • Genset runtime held under 3% of annual hours.
Your next step

Model your own off-grid case with the OPEX estimator, then submit a brief.

Project records are anonymised at the buyer's request and presented as planning-grade benchmarks. Costs, timelines and performance figures are indicative and are not engineering designs or quotations.

Supplier and manufacturer listings are provided for research, transparency and discovery only. ColdMatch Group does not provide automatic buyer-supplier introductions. Every cold chain project request is reviewed manually by David / ColdMatch Group, and supplier introductions are made only after internal approval.

More case studies
Get Free QuotesFind the Best Solution